First of all, I'm sorry that I couldn't suddenly update the notice for a long time. Currently, the release schedule is being delayed for a considerable amount of time due to various complicated situations internally. We should have delivered it as soon as possible, but the notice was delayed for a considerable period of time because we had to prioritize problem solving.
The reasons why the release schedule does not proceed are summarized in three briefly below.
Deterioration of buildings in the offices we are currently renting, mass leakage due to recent heavy rains, and abnormal operation of electrical facilities *This leak is currently occurring throughout the office.
Claiming more than insurance costs and management expenses for repairs and damages of the relevant building management office
Demand for the sudden disappearance of the lessee of the office under lease and the sale and eviction before the expiration of the lease through the auction of the leased office.
As a result, at this point, we urgently evicted and stored office equipment first, and the management office and We are in the process of requesting rights guarantees, related recovery, and damage compensation against tenants.
In addition, even the deposit has not yet been returned despite the need to rent a new office, and without notification to us The current system as the auction sale is carried out, overlapping the adjustment process for a number of additional issues and lease periods We are facing a situation where it is difficult to proceed with the scheduled game schedule.
Therefore, we are currently thinking of the following three possible alternatives.
Resume release schedule after completing new office lease and equipment transfer. -There is no additional development period, but the expected delay due to office rental and relocation is at least two months.
Once the online function is removed, the online function is added at the time when the office relocation is completed after pre-launching in offline mode. -Additional development period for change and redesign to offline mode occurs and requires about a month Most of the systems designed with the assumption of online functionality are separated, rebuilt, and destabilized.
After external hosting or renting a server to launch, transfer servers and data to existing equipment after completion of office relocation. -Although the launch schedule has the smallest delay range, the burden of expenditure is very high and the response speed is slow when problems such as service instability are caused.
In the above situation, several complex problems overlapped, so the update of the notice was delayed as we focused on solving the problem.
We will decide on an alternative plan as soon as possible and deliver it to you with additional notice.
Also, if you leave your opinion on the alternative plan in the comments of the notice, we will refer to the decision.
Once again, we are very sorry for the delay in delivering the contents, and we will deliver additional contents as soon as possible.